Sibur’s Nizhnekamsk styrene and polystyrene complex reaches 65% completion

Sibur has completed 65% of its new styrene and polystyrene production complex in Nizhnekamsk, with commissioning planned for 2028. The project will have annual capacity of 400,000 tonnes of styrene and 250,000 tonnes of polystyrene, targeting Russian demand and additional export opportunities.

Sibur’s Nizhnekamsk styrene and polystyrene complex reaches 65% completion

Construction advances at the Nizhnekamsk site

Sibur’s project to establish integrated styrene and polystyrene production at Nizhnekamskneftekhim in Nizhnekamsk has reached 65% overall completion, KazanFirst reported. Commissioning is scheduled for 2028. The development is intended to create a complete synthetic-materials chain at the site, converting ethylene into finished polymer granules.

Construction covers 38 hectares and includes two principal process units: an ethylbenzene and styrene plant and a polystyrene plant, alongside utilities and other common facilities. Contractors have installed 336 major equipment items. More than 90% of the planned reinforced-concrete structures are in place, while over 11,000 tonnes of steel structures have been erected, equal to 60% of the required volume. More than 170 pieces of construction equipment and over 3,000 people are involved in the project.

Annual capacity to reach 650,000 tonnes

The new units will be able to produce 400,000 tonnes of styrene and 250,000 tonnes of polystyrene per year. The product range will include high-impact polystyrene and general-purpose polystyrene. Sibur expects the output to serve Russian manufacturers in construction, automotive production, household appliances, packaging and medical products.

Work on the ethylbenzene and styrene unit includes the installation of a process furnace, which is 70% complete. At the polystyrene unit, reactor equipment has been installed together with 10 silos for finished-product storage and purification columns. Equipment for the flare system is in place at the common facilities, while preparations continue for the substations and control building. A nearby prefabrication workshop assembles, welds and tests pipeline sections before their installation at the main site. The workshop has already created more than 100 jobs.

Project linked to expanded ethylene production

The complex will use ethylene from Nizhnekamskneftekhim. Output of that feedstock at the company doubled following the 2025 launch of the EP-600 olefins complex. Sibur says the new chain will allow Russia to cover its domestic requirements for styrene, benzene and polystyrene with local production, reduce import dependence and create additional export potential. Domestic polystyrene currently accounts for about 85% of the Russian market, according to KazanFirst, and the company expects Russian production to raise that share to 100%.

Sibur is also assembling the future operating team. Around 300 high-technology positions are planned, including shift managers, engineers, process operators and maintenance specialists. Staffing is expected to be completed in the first quarter of 2027. The facility will use a domestically developed process-control system. The project forms part of Sibur’s investment program in Tatarstan, where the company has invested 406 billion rubles in production, maintenance, education and social infrastructure over 4.5 years. In the first half of 2026, Sibur’s Tatarstan businesses increased production by 6% year on year. Nizhnekamskneftekhim raised output by 6.4% to a record 1.6 million tonnes of commercial products.